Client: Public Building Commission of Chicago
Year: 2009-2010
Location 3250 W/ Adams, Chicago IL

This project was performed for the Public Building Commission of Chicago to improve the Marshall High School’s Campus Park. The approximate size of the jobsite was 8 acres.

The scope of this project included:

  • Demolition and Removal of Existing Campus Park
  • Installation of Sewer and Water Retention
  • Installation of Fire Hydrant and Water Lines
  • Installation of Concrete: Sidewalk, Alleys. Curb and Gutter
  • Installation of Paved Parking Lot
  • Installation of Electrical
  • Installation of Irrigation
  • Ornamental Fencing
  • Construction Fencing
  • Landscaping
  • Maintenance of Emergency Exits