Client – Chicago Dept. of Aviaton / O’Hare Modernization Program
Project – Runway 10R/28L Paving, Lighting and Signage

Overview – As a subcontractor to the Turner Acura Lindahl Triventure, McDonagh installed nine (9) manholes and catch basin structures with pipe runs from 18” to 54”. McDonagh also installed 47,000 LF of pvc underdrain with 137 inspection hole structures placed along the new runway and taxiways. Other responsibilities were extensive removal operations which included electrical duct bank from 2-way to 44-way, electrical and sewer structures, lift stations, and drainage pipe.