Client: Public Building Commission of Chicago
Year: 2009
Location 2200 N. Central Ave Chicago IL 60639
This project was performed to remediate the site for the
building of a new Chicago Public School.
- Removal of 18,000 Tons of Soil (Special Urban Waste)
- Backfill with Clean Fill
- Compaction of Clean Fill
- Building Footprint Preparation
- Installation of Water Retention System
- Installation of Sewer
- Installation of Water Supply to the Building and to Private Hydrants
- Installation of Irrigation System
- Installation of Landscaping
- Installation of Parking Lot to be used by the School and the Stadium.
- Installation of Signage
- Construction Fencing with Wind Screening
- Silt and Erosion Control
- LEED Project